Wellard Green — Release 12
CREW-2 · Brad · Friday 14 August
Crew
Add SV-26-0488 19 Aug 2026 · AM

Wellard Green — Release 12

Lots 340–351, Bombay Blvd, Wellard 6170

Barrier for the open day

What went in

Put in what you actually installed, not what was on the run sheet.

Temporary Fence — Standard
TF-STD · metres
+38.4 m

Photos

Before and after. If they ever say it wasn't done, this is what settles it.

No photos on this one yet.

Time on site

The price already covers 0.77 hours of one person's time for this much gear (about 50 m an hour). Put down what it actually took — the office works out the rest.

Allowed on this docket: 0.77 hrs.

It goes straight to the office. Nothing moves in the yard until they check it off.