J-26-0121
On siteHasler Road Commercial — Lot 447 · 112 Hasler Rd, Osborne Park 6017 · Standard Braced · Building & construction
On site right now
the sum of every completed movement on this job — not the estimate, not the load 492 m · 612 units| Item | Estimated | Loaded | Installed | Since install | On site now | Hire /block |
|---|---|---|---|---|---|---|
| TF-BRC Temporary Fence — Standard Braced | 319.2 m | 403.2 m | 372 m | +120 m | 492 m | $2.35 |
| BRC-KIT Bracing Kit | 43 | 56 | 51 | +5 | 56 | — |
| FT-PLAS Fence Foot — Plastic Filled | 289 | 318 | 273 | — | 273 | — |
| CLP-STD Fence Clamp — Standard | 274 | 304 | 271 | — | 271 | — |
| SIGN-SITE Site Safety Sign | 6 | 8 | 7 | — | 7 | $4.50 |
| GT-PED Pedestrian Gate Panel | 3 | 4 | 3 | — | 3 | $14.50 |
| GT-VEH Vehicle Gate — 6m Double Swing | 1 | 2 | 2 | — | 2 | $48.00 |
| Fence, metres | 319 m | 403 m | 372 m | +120 m | 492 m |
They asked for 319 m, the yard sent 403 m so the crew would not run short, and 372 m went in. The install invoice bills the installed figure — $4,916.80 ex GST, against $4,141.78 had it been billed on the estimate (+$775).
How it got there
2 completed visits since 03 July 2026.
The hire
- Booked
- 22 June 2026
- Installed
- 03 July 2026
- Agreed period
- 3 blocks · 12 weeks
- Off hire due
- 25 Sept 20262 days ago
- Site contact
- Marcus Devereux0419 003 552
- Their PO
- PO-412039
- Booked by
- JH
Site visits
every trip a crew has made or is booked to make — each one moves the running total| Visit | Type | Date | Crew | Status | What moved | Net metres | Invoice |
|---|---|---|---|---|---|---|---|
| SV-26-0399 docket D40239 | Install | 03 July 2026 AM | CREW-4 | Completed | +372 m TF-BRC +51 BRC-KIT +273 FT-PLAS +271 CLP-STD +3 | +372 m | INV-26-1018 |
| SV-26-0400 docket D40240 | Add | 22 July 2026 AM | CREW-5 | Completed | +120 m TF-BRC +5 BRC-KIT | +120 m | INV-26-1019 |
| SV-26-0467 docket D41880 | Add | 14 Aug 2026 AM | CREW-1 | On site | +122.4 m TF-BRC +10 BRC-KIT | +122.4 m | — |
| SV-26-0489 | Collect | 19 Aug 2026 PM | CREW-3 | Scheduled | −177.6 m TF-BRC −8 BRC-KIT −73 FT-PLAS | −177.6 m | — |
2 visits still open.
Invoices raised on this job
Account customer — invoiced on 30 days EOM| Invoice | What for | Issued | Period | Status | Ex GST |
|---|---|---|---|---|---|
| INV-26-1018 | Install | 03 July 2026 | 3 July – 25 Sept | Overdue | $5,605.55 |
| INV-26-1019 | Variation | 22 July 2026 | 22 July – 25 Sept | Sent | $1,211.00 |
| Billed on this job · $0.00 of it paid | $6,816.55 | ||||
Customer
- Contact
- Rhys Cattalini
- Phone
- 08 9261 4200
- ABN
- 59 008 924 353
- Segment
- Building & construction
Account customer, so this job is invoiced once the install is done and falls due on 30 days eom.
Purchase order required on every job. No PO, no dispatch.
Photos and paperwork
4 photos off the crews' iPads, and every docket raised against this site| Docket | Visit | When | Crew | Signed on site by | State | |
|---|---|---|---|---|---|---|
| D40239 | SV-26-0399 Install | 03 July 2026 | CREW-4 | Marcus Devereux | Approved | |
| D40240 | SV-26-0400 Add | 22 July 2026 | CREW-5 | Marcus Devereux | Approved | |
| D41880 | SV-26-0467 Add | 14 Aug 2026 | CREW-1 | Marcus Devereux | Submitted | |
| — | SV-26-0489 Collect | 19 Aug 2026 | CREW-3 | — | Not started |
Everything here is held with the job, not in a folder somewhere — so it is still attached to this site in two years when somebody asks what the frontage looked like before the crew started.
Conversation on this job
1 message — everything said about this, in one place- In Phone Extra run needed 09 Aug 2026, 7:25 pmMarcus Devereux → us
Gate access has moved to the southern end from Monday — passed to the crew.