CollectedWheatstone Module Yard · Onslow Rd, Onslow 6710 · Standard Braced with Total Block Out · Dust control
On site right now
the sum of every completed movement on this job — not the estimate, not the load 0 m| Item | Estimated | Loaded | Installed | Since install | On site now | Hire /mo |
|---|---|---|---|---|---|---|
| TF-BRC Temporary Fence — Standard Braced | 302.4 m | 369.6 m | 360 m | −360 m | — | $2.35 |
| SC-BLOK Total Block Out Screening | 303 m | 371 m | 319 m | −319 m | — | $1.75 |
| SC-STD Shade Cloth | 182 m | 260 m | 227 m | −227 m | — | $0.95 |
| FT-BLOK Fence Foot — Concrete Block | 273 | 296 | 278 | −278 | — | — |
| BRC-KIT Bracing Kit | 52 | 63 | 61 | −61 | — | — |
| Fence, metres | 787 m | 1,001 m | 906 m | −906 m | 0 m |
They asked for 787 m, the yard sent 1,001 m so the crew would not run short, and 906 m went in. The install invoice bills the installed figure — $9,901.70 ex GST, against $8,711.85 had it been billed on the estimate (+$1,190).
How it got there
5 completed visits since 22 Feb 2026.
The hire
- Booked
- 08 Feb 2026
- Installed
- 22 Feb 2026
- Agreed period
- 4 months
- Off hire due
- 22 June 202647 days ago
- Off hire requested
- 02 July 2026
- Collected
- 05 July 2026
- Site contact
- Tegan Ruddock0448 990 337
- Booked by
- KD
Site visits
every trip a crew has made or is booked to make — each one moves the running total| Visit | Type | Date | Crew | Status | What moved | Net metres | Invoice |
|---|---|---|---|---|---|---|---|
| SV-26-0437 docket D40400 | Install | 22 Feb 2026 AM | CREW-2 | Completed | +360 m TF-BRC +319 m SC-BLOK +227 m SC-STD +278 FT-BLOK +1 | +906 m | INV-26-1042 |
| SV-26-0438 docket D40401 | Collect | 01 Apr 2026 PM | CREW-3 | Completed | −132 m TF-BRC | −132 m | INV-26-1045 |
| SV-26-0439 docket D40402 | Add | 20 Apr 2026 AM | CREW-4 | Completed | +91.2 m TF-BRC | +91.2 m | INV-26-1043 |
| SV-26-0440 docket D40403 | Add | 01 June 2026 PM | CREW-5 | Completed | +112.8 m TF-BRC +39 m SC-BLOK | +151.8 m | INV-26-1044 |
| SV-26-0441 docket D40409 | Final collection | 05 July 2026 All day | CREW-4 | Completed | −432 m TF-BRC −351 m SC-BLOK −7 m SC-BLOK −220 m SC-STD +4 | −1,017 m | no charge |
Invoices raised on this job
Account customer — invoiced on 45 days EOM| Invoice | What for | Issued | Period | Status | Ex GST |
|---|---|---|---|---|---|
| INV-26-1042 | Install | 22 Feb 2026 | 22 Feb – 22 June | Paid | $9,901.70 |
| INV-26-1045 | Variation | 01 Apr 2026 | 1 Apr – — | Sent | $185.00 |
| INV-26-1043 | Variation | 20 Apr 2026 | 20 Apr – 22 June | Paid | $964.76 |
| INV-26-1044 | Variation | 01 June 2026 | 1 June – 22 June | Paid | $1,055.96 |
| INV-26-1046 | Damage & loss | 12 July 2026 | — | Paid | $581.00 |
| Billed on this job · $12,503.42 of it paid | $12,688.42 | ||||
Customer
Monadelphous Engineering Pty Ltd
Account 45 days EOM
- Contact
- Dean Kowalczyk
- Phone
- 08 9329 8600
- ABN
- 28 008 988 547
- Segment
- Mining & resources
Account customer, so this job is invoiced once the install is done and falls due on 45 days eom.
Mine-site work. Regional cartage, site inductions, dust-control screening on most runs.
Log a site visit
What the crew took out, or what came back. Completing it posts the movements and the running total, the yard and the continuation rate all follow.
Edit J-26-0144
Site details and the agreed hire period.