the sum of every completed movement on this job — not the estimate, not the load 74 m · 228 units| Item | Estimated | Loaded | Installed | Since install | On site now | Hire /mo |
|---|---|---|---|---|---|---|
| TF-STD Temporary Fence — Standard | 57.6 m | 67.2 m | 60 m | +14.4 m | 74.4 m | $1.80 |
| FT-PLAS Fence Foot — Plastic Filled | 116 | 140 | 129 | +22 | 151 | — |
| CLP-STD Fence Clamp — Standard | 58 | 68 | 65 | +10 | 75 | — |
| GT-PED Pedestrian Gate Panel | 1 | 2 | 2 | — | 2 | $14.50 |
| Fence, metres | 58 m | 67 m | 60 m | +14.4 m | 74 m |
They asked for 58 m, the yard sent 67 m so the crew would not run short, and 60 m went in. The install invoice bills the installed figure — $704.00 ex GST, against $644.16 had it been billed on the estimate (+$60).
How it got there
2 completed visits since 26 May 2026.
The hire
- Booked
- 17 May 2026
- Installed
- 26 May 2026
- Agreed period
- 2 months
- Off hire due
- 26 July 202613 days ago
- Off hire requested
- 05 Aug 2026
- Site contact
- Marcus Devereux0419 003 552
- Booked by
- MC
Continuation of hire
past 26 July 2026 by 1 month — charged per metre, per month, on what is on site now| Item | On site | Rate | Per month | 1 month |
|---|---|---|---|---|
| GT-PED Pedestrian Gate Panel | 2 | $14.50 / unit / month | $29.00 | $29.00 |
| TF-STD Temporary Fence — Standard | 74.4 m | $1.80 / m / month | $133.92 | $133.92 |
| Accrued and not yet raised | $162.92 | $162.92 | ||
Site visits
every trip a crew has made or is booked to make — each one moves the running total| Visit | Type | Date | Crew | Status | What moved | Net metres | Invoice |
|---|---|---|---|---|---|---|---|
| SV-26-0426 docket D40344 | Install | 26 May 2026 AM | CREW-4 | Completed | +60 m TF-STD +129 FT-PLAS +65 CLP-STD +2 GT-PED | +60 m | INV-26-1039 |
| SV-26-0427 docket D40345 | Add | 14 June 2026 AM | CREW-5 | Completed | +14.4 m TF-STD +22 FT-PLAS +10 CLP-STD | +14.4 m | INV-26-1040 |
| SV-26-0467 | Add | 09 Aug 2026 PM | CREW-4 | Dispatched | +12 m TF-STD | +12 m | — |
| SV-26-0471 | Inspection | 09 Aug 2026 All day | CREW-3 | Scheduled | +2.4 m TF-STD | +2.4 m | no charge |
| SV-26-0428 | Final collection | 10 Aug 2026 AM | CREW-1 | Scheduled | Final collection — already billed on the install invoice | — | no charge |
| SV-26-0475 | Collect | 10 Aug 2026 PM | CREW-2 | Scheduled | −16.8 m TF-STD | −16.8 m | — |
| SV-26-0479 | Add | 11 Aug 2026 PM | CREW-1 | Scheduled | +9.6 m TF-STD | +9.6 m | — |
| SV-26-0483 | Add | 12 Aug 2026 PM | CREW-5 | Scheduled | +24 m TF-STD +42 FT-PLAS +20 CLP-STD | +24 m | — |
| SV-26-0487 | Collect | 16 Aug 2026 AM | CREW-4 | Scheduled | −24 m TF-STD | −24 m | — |
| SV-26-0491 | Add | 16 Aug 2026 AM | CREW-3 | Scheduled | +9.6 m TF-STD +27 FT-PLAS +12 CLP-STD | +9.6 m | — |
| SV-26-0495 | Collect | 18 Aug 2026 AM | CREW-2 | Scheduled | −19.2 m TF-STD −62 FT-PLAS −19 CLP-STD | −19.2 m | — |
| SV-26-0499 | Repair | 24 Aug 2026 AM | CREW-1 | Scheduled | +2.4 m TF-STD +1 FT-PLAS | +2.4 m | no charge |
10 visits still open.
Invoices raised on this job
Account customer — invoiced on 30 days EOM| Invoice | What for | Issued | Period | Status | Ex GST |
|---|---|---|---|---|---|
| INV-26-1039 | Install | 26 May 2026 | 26 May – 26 July | Paid | $704.00 |
| INV-26-1040 | Variation | 14 June 2026 | 14 June – 26 July | Paid | $254.12 |
| Billed on this job · $958.12 of it paid | $958.12 | ||||
Customer
Dale Alcock Homes Pty Ltd
Account 30 days EOM
- Contact
- Bree Tunstill
- Phone
- 08 9242 6000
- ABN
- 20 009 264 464
- Segment
- Housing
Account customer, so this job is invoiced once the install is done and falls due on 30 days eom.
Housing sites — standard 6m frontage package, mostly TF-STD.
Log a site visit
What the crew took out, or what came back. Completing it posts the movements and the running total, the yard and the continuation rate all follow.
Edit J-26-0136
Site details and the agreed hire period.