J-26-0137
On site Continuation of hireEllenbrook Display Village · The Broadway, Ellenbrook 6069 · Standard · Display & estate frontage
On site right now
the sum of every completed movement on this job — not the estimate, not the load 210 m · 217 units| Item | Estimated | Loaded | Installed | Since install | On site now | Hire /block |
|---|---|---|---|---|---|---|
| WPF-STD White Picket Fence | 140 m | 176 m | 144 m | — | 144 m | $4.20 |
| MNR-STD Manor Fence | 62 m | 80 m | 66 m | — | 66 m | $4.60 |
| FT-PLAS Fence Foot — Plastic Filled | 108 | 124 | 116 | — | 116 | — |
| CLP-STD Fence Clamp — Standard | 101 | 115 | 101 | — | 101 | — |
| Fence, metres | 202 m | 256 m | 210 m | +0 m | 210 m |
They asked for 202 m, the yard sent 256 m so the crew would not run short, and 210 m went in. The install invoice bills the installed figure — $3,298.90 ex GST, against $3,179.90 had it been billed on the estimate (+$119).
How it got there
1 completed visit since 17 June 2026.
The hire
- Booked
- 01 June 2026
- Installed
- 17 June 2026
- Agreed period
- 2 blocks · 8 weeks
- Off hire due
- 12 Aug 202646 days ago
- Site contact
- Aleks Radojevic0422 118 904
- Their PO
- DALE-21133
- Booked by
- KD
Continuation of hire
past 12 Aug 2026 by 2 blocks · 8 weeks — charged per metre, per four-week block, on what is on site now| Item | On site | Rate | Per block | × 2 |
|---|---|---|---|---|
| MNR-STD Manor Fence | 66 m | $4.60 / m / month | $303.60 | $607.20 |
| WPF-STD White Picket Fence | 144 m | $4.20 / m / month | $604.80 | $1,209.60 |
| Accrued and not yet raised | $908.40 | $1,816.80 | ||
Site visits
every trip a crew has made or is booked to make — each one moves the running total| Visit | Type | Date | Crew | Status | What moved | Net metres | Invoice |
|---|---|---|---|---|---|---|---|
| SV-26-0428 docket D40351 | Install | 17 June 2026 AM | CREW-5 | Completed | +144 m WPF-STD +66 m MNR-STD +116 FT-PLAS +101 CLP-STD | +210 m | INV-26-1044 |
| SV-26-0479 | Add | 17 Aug 2026 All day | CREW-3 | Scheduled | +44 m WPF-STD +18 m MNR-STD | +62 m | — |
| SV-26-0501 | Add | 28 Aug 2026 AM | CREW-5 | Scheduled | +56 m WPF-STD +10 m MNR-STD | +66 m | — |
2 visits still open.
Invoices raised on this job
Account customer — invoiced on 30 days EOM| Invoice | What for | Issued | Period | Status | Ex GST |
|---|---|---|---|---|---|
| INV-26-1044 | Install | 17 June 2026 | 17 June – 12 Aug | Overdue | $3,441.40 |
| Billed on this job · $0.00 of it paid | $3,441.40 | ||||
Customer
- Contact
- Bree Tunstill
- Phone
- 08 9242 6000
- ABN
- 20 009 264 464
- Segment
- Housing
Account customer, so this job is invoiced once the install is done and falls due on 30 days eom.
Housing sites — standard 6m frontage package, mostly TF-STD.
Photos and paperwork
nothing filed against this site yet| Docket | Visit | When | Crew | Signed on site by | State | |
|---|---|---|---|---|---|---|
| D40351 | SV-26-0428 Install | 17 June 2026 | CREW-5 | Aleks Radojevic | Approved | |
| — | SV-26-0479 Add | 17 Aug 2026 | CREW-3 | — | Not started | |
| — | SV-26-0501 Add | 28 Aug 2026 | CREW-5 | — | Not started |
Everything here is held with the job, not in a folder somewhere — so it is still attached to this site in two years when somebody asks what the frontage looked like before the crew started.