All Fence
All Fence U Rent
INV-26-1055 Demo Continuation of hire · Main Roads Western Australia
Xero · synced 9:14 am 27 Sept 2026

INV-26-1055

Continuation of hire Paid Xero INV-9049

Main Roads Western Australia · J-26-0147 Great Eastern Highway — Bilgoman Realignment

All Fence U Rent
All Fence U Rent Pty Ltd · ABN 24 128 604 973
80 Collingwood St, Osborne Park WA 6017
0408 877 300 · hire@allfenceurent.com.au
100% WA owned and operated
Tax invoice
INV-26-1055
22 May 2026
Period 24 Apr 2026 – 22 May 2026
Invoice to
Main Roads Western Australia
Priya Raghavan
Don Aitken Centre, Waterloo Cr
East Perth WA 6004
ABN 50 860 676 021
Site
Great Eastern Highway — Bilgoman Realignment
Great Eastern Hwy
Glen Forrest WA 6071
Job J-26-0147 · your PO Not provided
Standard Braced with Total Block Out
Issued
22 May 2026
Terms
30 days EOM
Due
01 June 2026
Status
Paid 25 June 2026

Continuation

Per metre, per four-week block, on the equipment standing on site — not on what was quoted. $2,859.20
DescriptionQtyUnitAmount
Continuation of hire — Temporary Fence — Standard Braced · per metre, per four-week blockTF-BRC 672 m $2.35 $1,579.20
Continuation of hire — Total Block Out Screening · per metre, per four-week blockSC-BLOK 656 m $1.75 $1,148.00
Continuation of hire — Site Safety Sign · per unit, per four-week blockSIGN-SITE 8 $4.50 $36.00
Continuation of hire — Vehicle Gate — 6m Double Swing · per unit, per four-week blockGT-VEH 2 $48.00 $96.00
Subtotal ex GST
$2,859.20
GST 10%
$285.92
Total due
$3,145.12
Paid 25 June 2026
$3,145.12
Payment
NAB · BSB 086-006 · Account 44 921 8807
All Fence U Rent Pty Ltd
Please quote INV-26-1055 as the reference.
Notes
Hire continued past the agreed period · checked and approved before it went out

All Fence U Rent Pty Ltd · ABN 24 128 604 973 · 80 Collingwood St, Osborne Park WA 6017 · 0408 877 300 · hire@allfenceurent.com.au

Amount

$3,145.12
$2,859.20 ex GST + $285.92 GST
Kind
Continuation of hire
Lines
4
Terms
30 days EOM
Xero
INV-9049
Why this is the amount

The agreed period ended 24 Apr 2026 and the equipment is still on site. This is the per-metre-per-block rate applied to what was standing there over 24 Apr 2026 – 22 May 2026 — the running total, not the original quantity.