SV-26-0444
Final collection Completed No chargeVisit 4 of 5 on J-26-0146 · Collie Battery Site — Perimeter, Collie
All Fence U Rent Pty Ltd · ABN 24 128 604 973
80 Collingwood St, Osborne Park WA 6017
0408 877 300 · hire@allfenceurent.com.au
100% WA owned and operated
80 Collingwood St, Osborne Park WA 6017
0408 877 300 · hire@allfenceurent.com.au
100% WA owned and operated
Final collection docket
SV-26-0444
29 June 2026
Docket D40423
Site
Collie Battery Site — Perimeter
Coalfields Hwy
Collie WA 6225
Site contact Priya Nandakumar · 0455 771 209
Collie WA 6225
Site contact Priya Nandakumar · 0455 771 209
Customer
Decmil Australia Pty Ltd
ABN 36 009 434 927
Hamish Purcell
08 9368 8877
Hamish Purcell
08 9368 8877
Job
J-26-0146
Crew
CREW-1Ricky
Truck
1GJP 442
Completed
29 June 2026, 4:01 pm
| Item | Description | Out to site | Back to yard | Condition | On site after |
|---|---|---|---|---|---|
| TF-BRC | Temporary Fence — Standard Braced 2.4m × 1.8m panel with bracing stay and second foot every third panel | — | 736.8 m | Good | 0 m |
| TF-BRC | Temporary Fence — Standard Braced 2.4m × 1.8m panel with bracing stay and second foot every third panel | — | 24 m | Damaged | 0 m |
| TF-BRC | Temporary Fence — Standard Braced 2.4m × 1.8m panel with bracing stay and second foot every third panel | — | 14.4 m | Missing | 0 m |
| SC-BLOK | Total Block Out Screening Solid block-out screening, 1.8m, wind-slit at 1.2m centres | — | 385 m | Good | 0 m |
| BRC-KIT | Bracing Kit Stay, second foot and two clamps, made up in the yard | — | 79 | Good | 0 |
| BRC-KIT | Bracing Kit Stay, second foot and two clamps, made up in the yard | — | 2 | Damaged | 0 |
| FT-BLOK | Fence Foot — Concrete Block 32kg concrete block foot, for wind-exposed and coastal runs | — | 367 | Good | 0 |
| CLP-STD | Fence Clamp — Standard Galvanised panel clamp, 17mm bolt | — | 399 | Good | 0 |
| CLP-STD | Fence Clamp — Standard Galvanised panel clamp, 17mm bolt | — | 12 | Damaged | 0 |
| BW-COIL | Barbed Wire Coil — 100m Three-strand barbed topping, 100m coil, brackets included | — | 7 | Good | 0 |
| SIGN-SITE | Site Safety Sign 600 × 450 site safety sign, cable-tied to the run | — | 8 | Good | 0 |
| BIN-3 | Containment Bin — 3m³ 3m³ rubbish containment bin, lidded, hook-lift compatible | — | 3 | Good | 0 |
| Fence, metres | — | 1,160 m | 0 m | ||
Notes: Final collection — billed on the install invoice
Crew signature
Site signature
Date
All Fence U Rent Pty Ltd · ABN 24 128 604 973 · 80 Collingwood St, Osborne Park WA 6017 · 0408 877 300. The quantities on this docket are what gets invoiced. Equipment remains the property of All Fence U Rent Pty Ltd for the duration of the hire; anything not returned is charged at the replacement rate.
What this visit changes
Posted on 29 June 2026, 4:01 pm. It put nothing out and brought 1,160 m back, which is why J-26-0146 now shows 0 m on site.
- Movements posted
- 12
- Yard adjusted
- 12 lines
- Docket
- D40423
Came back short or damaged
Temporary Fence — Standard Braced
24 m · $19.00 each
Temporary Fence — Standard Braced
14.4 m · $54.00 each
Bracing Kit
2 · $16.00 each
Fence Clamp — Standard
12 · $3.00 each
Charged on a damage and loss invoice once the yard has assessed it, off the job.